Jay Dee Contractors

15 Mile Road Interceptor Repair – Lining of Interceptor

Macomb County


Project Overview

Following the collapse of the sewer interceptor along 15 Mile Road in 2016, which caused a significant sinkhole and sewage spill of nearly 13 million gallons of raw sewage into the Clinton River, emergency repairs were executed. The repair involved the installation of 3,700 ft. of 9 ft. 2 in. diameter carbon fiber reinforced polymer pipe (CCFRP) inside the damaged interceptor within a stringent 30-day timeline.

Project Stats

Project Owner


Macomb County

Services


  • Tunnel Rehabilitation

Markets


  • Sanitation & Wastewater

Location


, MI

Completion Year


2018

Project Value


$2.8 million

Project Size


  • 3,700 ft of 9 ft 2 inch diameter pipe and tunnel fiberglass reinforced polymer (FRP)
  • 3,600 cubic yards of cellular grout backfill

Contract Type


Design-Bid-Build