Spring/Fishburne US 17 Drainage Improvements – Division I (Phase 3) – Tunnels and Shafts

City of Charleston


Project Overview

Aiming to alleviate flooding in significant portions of Charleston, this project involved constructing four access shafts, 7,250 ft. of deep stormwater conveyance tunnels, eight adit tunnels, and a near-surface collection system. Challenges included working in historic, densely populated neighborhoods and managing construction in an active floodplain within the Atlantic Hurricane basin.

Project Stats

Project Owner


City of Charleston

Services


  • TBM Tunnel Excavation
  • Shaft Excavation
  • Structure Construction
  • Sequential Excavation Method

Markets


  • Stormwater Management

Location


Charleston, SC

Completion Year


2020

Project Value


$33.6 million

Project Size


  • 5,375 ft of 12 ft ID cast in place stormwater tunnel
  • 1,986 ft of 8 ft ID cast in place stormwater tunnel
  • 4 access in drop shafts between 20 and 30 ft diameter and up to 170 ft deep
  • 8 - 8 ft diameter adit tunnels totaling 950 ft in length

Contract Type


Design-Bid-Build