Designed to alleviate sewer backups and reduce surface flooding, this project involved the construction of 2,500 ft. of 78 in. diameter RCP via pipe jacking, 4 ea. rib & lag shafts, and a 232 ft. deep drop shaft that connected to an existing 13 ft. 9 in. tunnel. The drop shaft was excavated by drilling & blasting. Key challenges included live connection work from the drop shaft to the existing 13 ft. 9 tunnel, and working within Chicago city limits and the minimal right-of-way given to construct the project.
City of Chicago Department of Water Management
Chicago, IL
2016
$20.4 million
Design-Bid-Build